Return To Main Page
Contact Us

March 24, 2024
By Joshua Haiar -  South Dakota Searchlight

Regulators approve early start for largest solar farm in SD; Basin Electric to buy the power

Utility regulators took actions this month that will allow a solar energy project to start producing electricity ahead of schedule at the largest solar farm in South Dakota.
Bismarck-based Basin Electric Power Cooperative will buy the power. Basin Electric serves numerous rural electric co-ops across the region.
 
Wild Springs Solar’s $190 million project sprawls across areas totaling 1,499 acres -- about 2 square miles -- of ranchland in Pennington County, just south of New Underwood. The project was built by National Grid Renewables, of Bloomington, Minnesota, South Dakota Searchlight reported.
 
The project’s construction phase may conclude ahead of schedule. So, the company requested a change to its permit conditions that will allow it to start operations as sooner than the previously anticipated date of May 1.

The state Public Utilities Commission required the solar farm to post a surety bond to make sure there is enough money to safely remove the solar panels and clean up the site when the solar farm is no longer used. The initial bond amounts were $2.5 million and then $3 million. The new surety bond amount is $4.14 million.
 

The changes in the bond amount reflect changing estimates of the future decommissioning costs. The changing cost estimates are due to the fluctuating value of scrap steel. If the solar farm is shut down, some of the steel could be sold for scrap to offset the cost of decommissioning the project.
 
“The price of HMS (scrap steel) in August 2022 was $505 whereas it is now $325 in January 2024,” the company wrote. An attorney for the company, Mollie Smith, said that was partly due to high demand as supply chain problems arose during the COVID-19 pandemic.
 
“Things were in high demand and it was difficult to get them,” Smith told the commission.
The project can produce up to 128 megawatts of electricity. South Dakota had only 102 megawatts of capacity from other solar projects at the end of last year, ranking 47th in the nation, according to the Solar Energy Industries Association. Those 102 megawatts were enough to power about 12,000 homes.
Between projects like Wild Springs and the 80-megawatt Fall River Solar project, solar electricity generation in South Dakota is expected to rise by 328 megawatts in the next five years. Fall River Solar is a 500-acre solar farm in Fall River County near Oelrichs.

 

Green Play Ammonia™, Yielder® NFuel Energy.
Spokane, Washington. 99212
www.exactrix.com

509 995 1879 cell, Pacific.
exactrix@exactrix.com